Reconstruction of the existing pump station “Sever 4” and the construction of a new pump station “Ratno ostrvo” were executed to meet the requirements of PE “Waterworks and Sewerage”. These two pump stations are connected by GRP pipes, while the outflow into the Danube includes ductile pipes.
Employer |
||
PE Waterworks and Sewerage, Novi Sad |
||
Pump stations |
||
Sever 4 - pump capacity |
3 x 250 |
l/s |
power |
3 x 50 |
KW |
Ratno ostrvo – pump capacity |
3 x 250 |
l/s |
power |
3 x 35 |
KW |
Pipelines |
||
total length |
2,300 |
m |
excavation |
18.000 |
m3 |
embankment |
50.00 |